Winter Construction Notice

(Windsor to Hamilton/Halton/Oakville, Mount Forest (Hwy 9/109) south to Port Rowan).

If you are conducting business in the South (as defined above), here are some important timelines to keep in mind:

Between October 31 and March 31, we will do our best to meet our standard timelines, but we will be adding two weeks to the installation date to account for winter conditions.

If Service Main is required, please ensure that your request is received no later than September 30 to facilitate installation by the end of the calendar year. Requests received after September 30 may be scheduled for installation in the spring when weather and construction conditions allow.

(Mount Forest (Hwy 9/109) north to Wiarton and over to Owen Sound/Collingwood).

If you are conducting business in the South area, as defined above, here are the dates that apply:

All gas service applications, on a service main, must be received no later than September 30 in order to facilitate gas service installation by the end of the calendar year. Please be advised, any applications for gas service received after this deadline will be scheduled for installation after May 1 (approximately), but may not be installed after June 30. If the schedule allows, an earlier installation may occur.

For service main requests received after the August 30 deadline, the main may not be installed until after June 30 of the following year.

Winter Construction for Union Gas North

(Orillia to North Bay to Sault Ste. Marie to Englehart , and surrounding area)

If you are conducting business in the East and/or North area, as defined above, here are the dates that apply to your customers:

All gas service applications, on main, must be received by Union Gas no later than September 30 in order to facilitate gas service installation prior to the end of the calendar year.

Please be advised, any applications for gas service received after this deadline will be scheduled for installation after May 1 (approximately) but may not be installed until June 30. If the schedule allows, an earlier installation may occur.

For conversion or commercial customers, where new main is required, submit your request no later than August 30.

For main requests received after the August 30 deadline, main may not be installed until June 30 of the following year.

In the North, during winter conditions the LCID does not apply where builder supplied trenches have been pre-approved by the local construction.

Winter Construction for Union Gas West

(Kirkland Lake to Thunder Bay to Kenora, and surrounding areas, Including Red Lake)

If you are conducting business in the Western area, as defined above, here are the dates that apply to your customers:

All gas service applications, on main, must be received by Union Gas no later than September 30 in order to facilitate gas service installation prior to the end of the calendar year.

Please be advised, any applications for gas service received after this deadline will be scheduled for installation after May 1 (approximately) but may not be installed until June 30. If the schedule allows, an earlier installation may occur.

For conversion or commercial customers, where new main is required, submit your request no later than August 30.

For main requests received after the August 30 deadline, main may not be installed until June 30 of the following year.

In the West, during winter conditions the LCID does not apply where builder supplied trenches have been pre-approved by the local construction

Winter Construction for Union Gas East

(Cobourg to Cornwall)

If you are conducting business in the East and/or North area, as defined above, here are the dates that apply to your customers:

All gas service applications, on main, must be received by Union Gas no later than September 30 in order to facilitate gas service installation prior to the end of the calendar year.

Please be advised, any applications for gas service received after this deadline will be scheduled for installation after May 1 (approximately) but may not be installed until June 30. If the schedule allows, an earlier installation may occur.

For conversion or commercial customers, where new main is required, submit your request no later than August 30.

For main requests received after the August 30 deadline, main may not be installed until June 30 of the following year.

In the East, the LCID does not apply to new build, residential subdivisions on main.

Winter Construction Notices